4th Avenue North (East of 10th Street)
Water Main Replacement & Street Reconstruction
Current Status: Updated October 26, 2012
All phases are open to traffic.
A Look Ahead
Any final items will be completed without closures.
Project Scope
This project includes replacing the aging water main and deteriorated street paving. It also includes new sidewalks, driveways & street lighting.
This project will include the closure of 10th St. N. at 4th Ave. N. This closure will be in place a maximum of 30 days.
Project Schedule and Completion
• Projected start date: July 9, 2012.
• This project has 5 phases, each of which will take approximately 45 days to complete (multiple phases may be under construction at the same time).
• Substantial completion date: October 5, 2012.