4th Avenue North (West of 10th Street)

Water Main Replacement & Street Reconstruction

Current Status: Updated October 15, 2012

Phases 1 - 3 & 5: Open.

Phase-4: Paving operations wrapping up.

A Look Ahead

Phase-1 - 3 & 5: Open.

Phase-4: Opening the week of Oct. 15.

Project Scope

This project includes replacement of the aging water main and deteriorated street paving. It also includes new sidewalks, driveways & street lighting.

Project Schedule and Completion

•      Projected start date: June 12, 2012
•      This project has 5 phases, each of which will take approximately 45 days to complete (multiple phases may be under construction at the same time).
•      Substantial completion date: October 5, 2012