4th Avenue North (West of 10th Street)
Water Main Replacement & Street Reconstruction
Current Status: Updated October 15, 2012
Phases 1 - 3 & 5: Open.
Phase-4: Paving operations wrapping up.
A Look Ahead
Phase-1 - 3 & 5: Open.
Phase-4: Opening the week of Oct. 15.
Project Scope
This project includes replacement of the aging water main and deteriorated street paving. It also includes new sidewalks, driveways & street lighting.
Project Schedule and Completion
• Projected start date: June 12, 2012
• This project has 5 phases, each of which will take approximately 45 days to complete (multiple phases may be under construction at the same time).
• Substantial completion date: October 5, 2012