52nd Avenue South Reconstruction
Impovement District Number 5314
%20OverAllMap%20-%20Rvsd%205-20-08.jpg)
Nature and Scope
This project includes the following:
1. Construction of 52nd Avenue South from University Drive to 45th Street
South to include:
- Converting a rural asphalt roadway to an:
- urban 5-lane concrete pavement from University Drive to 31st Street.
- urban 7-lane concrete pavement from 31st Street to 38th Street.
- urban 5-lane concrete pavement from 38th Street to 45th Street.
- Construction to include:
- Storm sewer system
- Urban street lighting
- Bike trail/sidewalks
- Traffic signals installed at 45th Street, 42nd Street, 38th Street, east and west interstate ramps, 25th Street and Bishops Boulevard.
2. Construction of I-29 interchange to include all quadrant ramps and adjacent
frontage roads (NDDOT portion of project).
To learn more about the North Dakota Department of Transportation
(NDDOT) work on 52nd Avenue South and Interstate 29, visit
NDDOT/52nd Avenue South Interchange.
3. Installation of water main distribution lines.
4. Installation of water main transmission line
Purpose
These projects are on the arterial street system and are necessitated by the traffic demands of large commercial and residential developments east and west of I-29 along 52nd Avenue South. This project is to convert the current rural roadway with ditches into an elevated urban roadway section. This section will correct several deficiencies, including insufficient capacity, inadequate access and deteriorated pavement. These improvements will provide access to allow development to occur in this area.
Project Completion
Reconstruction is scheduled to be complete by approximately Nov. 16, 2008.