City Commission selection of preferred base alternative
June 30, 2008
Public input meetings
April 15 - August 2008
Project design, right-of-way acquisition and permitting
July 2008 - October 2009
Begin construction
June 2009
Functional completion
March 2011
Final completion
July 2012