City Commission selection of preferred base alternative
July, 2008
Public input meetings
April, 2008 - September, 2008
Project design, right-of-way acquisition and permitting
July, 2008 - October, 2009
Begin construction
June, 2009
Functional completion
March, 2011
Final completion
July, 2012